High-speed

Off the rails – will California ever get its high-speed rail? 

The California High-Speed Rail project continues to receive attention – often the subject of press headlines both good and bad. But where is it now and what can we expect next? Andrew Tunnicliffe tries to unpick events.

F

or a country that was built on the railroad, the now years-old saga of the California High-Speed Rail project continues to enthral, depress and at times amuse Americans in almost equal measure. It’s a story of claim and counterclaim, allegation, and even insult.   


Almost 15 years ago Californians were promised a high-speed rail service between two of its great cities – Los Angeles (LA) and San Francisco – in just two hours and 40 minutes. It was a “moon shot” that required technological innovation, big thinking, political consensus, and a sizeable budget. Instead, it’s been mired with delay, overspending, political strife, and questionable decision-making.  
 
Below is a timeline of the history of high-speed rail, including some of the most noteworthy moments. 

1996

Breaking ground

A high-speed rail link across California is first mooted. State Governor, Pete Wilson, established the California High-Speed Rail Authority (CHSRA), with the aim of developing a proposal to present to both him and state legislatures, before giving Californians a public vote.

The general economic coronavirus aid of the federal government that has been initiated so far does not offer effective help

1996–2000

A detailed study found high-speed rail lines to be economically, environmentally and socially profitable and as such work got underway to develop a strategic plan and project proposal.


After the completion of a business plan, the CHSRA sought input from international counterparts, hiring consultancies on high-speed rail projects to peer review their proposal, including SNCF (France), DE Consult (Germany) and JARTS (Japan).

August 2005

An implementation plan – which estimates the project would take between eight to 11 years to complete – is finally approved.

2008

It took another three years before elements of the proposal were put to voters. Proposition 1A, which the public agreed to at state elections in November, approved the sale of almost $10bn of bonds to fund the project. At the time, the network was penned to be completed by 2020, connecting LA and San Francisco through a series of high-speed segments that would see trains travel at around 350km/h. It would eventually run through Southern California, Sacramento San, Joaquin Valley, and the San Francisco Bay Area.

January 2009

Optimism for the project is high, boosted further with the inauguration of President Barack Obama, whose administration was laser focused on battling the deepening crisis ravaging the world’s economies and financial markets. As part of that fightback, Obama committed to a national plan of public spending, which included laying 13,840km of high-speed track. This already ambitious target then increased to 19,312km.

The 3,573-foot Tule River Viaduct, located south of the Tule River. Credit: California High-Speed Rail Authority.

2011–2012

Tensions simmer over plans for the infrastructure project and the damage it might do to communities and wildlife. The project, and its management, are criticised for some of the proposals, how they’ve been conveyed and, according to some, how community concerns have been ignored.

July 2012

After a lengthy period of research, environmental studies, and public consultation; a funding bill that would provide financial support for the construction of a 209km stretch of the project is signed in July 2012. The green light was given for work to commence on a 104.6km section by the US Federal Railroad Administration in September.

Early 2013

The $1bn Construction Package 1 contract, which involves the first 46.6km section between Madera and Fresno, is signed. By now commentary on the project is less favourable, thanks to perceived failings of the bidding process that, some argued, resulted in a less competent bidder winning. 


Responding to a negative critique published by the Los Angeles Times, CHSRA CEO Jeff Morales writes to the publication’s editor stating: “We utterly reject the thesis… that our procurement process has been anything but open, competitive, objective, and in accordance with the law.” The issues plague the authority for some time after. 

August 2014

The second significant construction contract, worth $71.86m, for design and construction oversight for Construction Package 2–3, is signed. It covers the Initial Operating Section of the high-speed rail programme, extending approximately 104km from the terminus of Construction Package 1 at East American Avenue in Fresno to 1.6km north of the Tulare-Kern County line.

January 2015

Ground is finally broken, with work commencing on the first part of the line in Freson. The project will result in a section of track stretching 273.6km, to be completed by 2028. The same month another contract was awarded; this time for a 96.5km section. 


There is also a request for a proposal made for rolling stock, eliciting interest from numerous suppliers. 

Ironworkers at the 2,000-foot Conejo Viaduct. Credit: California High-Speed Rail Authority

2016–17

Work continues, both at a project and finance management level and on the ground at construction sites. However delays, criticism, and often less than favourable press – particularly from the project’s staunch opponents – remain.

March 2018

CHSRA announces “the first significant construction” with foundation works beginning for a bridge that will carry high-speed trains over Garces Highway in Kern County.

November 2018

In a damming audit by the state, the project’s management team is left reeling by suggestions of flawed decision-making and poor contract management, which have together left it still 15 years away from completion and now costing $77bn – significantly higher than the $40bn initially forecasted.  


Having called for the audit with a Democrat counterpart, state Republican Jim Patterson said the project was now “dead in the water,” adding: “There will never be a completed track from the Bay Area to Los Angeles… The best we can hope for is a rump railroad running from Bakersfield to Madera.”

February 2019

In his first state of the state address, Governor Gavin Newsom shocks many by curtailing the ambitions of the project, arguing in its current form the plan would “cost too much and take too long”. He said there simply wasn’t “a path to get from Sacramento to San Diego, let alone from San Francisco to LA”. He did, however, signal his appetite to for ahead with a section between Merced and Bakersfield.

  

Later, President Trump blasts the project, calling for $3.5bn of federal funding already given to be returned. His words were put into action by the Department of Transport, which said it would consider withholding $929m earmarked for the project but not yet given.

Hanford Viaduct, the largest high-speed rail structure in the Central Valley spanning nearly 6,330 feet. Credit: California High-Speed Rail Authority

May 2019

In a major blow and politically explosive move, the Trump administration confirms this. The Federal Railroad Administration says the CHSRA had “repeatedly failed to comply with the terms” of a financial package agreement reached in 2010, and that it had “failed to make reasonable progress on the project”.  


“California has abandoned its original vision of a high-speed passenger rail service connecting San Francisco and Los Angeles, which was essential to its applications for FRA grant funding,” it said.


The move sparked fury among management and state political leaders, with Newsom responding: “This is California’s money, appropriated by Congress, and we will vigorously defend it in court.”

Late July 2019

In a double boost for the project, CHSRA says it has received “important federal approval” allowing it to “progress on the nation’s first high-speed rail system”. The authorisation given by the Federal Railroad Administration brings the completion of the environmental reviews a step closer.


Less than a week later and parts of Construction Package 1 are opened. They are the first completed high-speed rail grade separations under the first phase of the project. By the end of the year, a total of 30 major construction projects are ongoing across 191km of the route.  

Mid 2020

The Covid-19 pandemic begins to impact; in particular public consultations and meetings suffer, leading to extensions in the consultation process.

The San Joaquin River Viaduct, a 4,740-foot bridge over the San Joaquin River. Credit: California High-Speed Rail Authority

September 2020

CHRA CEO Brian Kelly says the Board of Directors has approved the Final Supplemental Environmental Impact Report/Environmental Impact Statement for Central Valley Wye – an 80km project alignment section. The decision means full environmental clearance has been given for the high-speed rail alignment between Merced and Bakersfield.

Late 2020

With construction continuing the CHRA appears buoyed by its achievements during “a difficult year”. In November, the American Avenue overpass in Fresno County is opened, becoming the fifth high-speed rail structure to open in the Central Valley in just three months. 


CHRA also announces an employment milestone – having created 5,000 construction jobs in the Central Valley area since work began. Tom Richards, CHRA chairman declares: “There is no question that high-speed rail is happening in California.” 

Early 2021

After what was a more positive year for the CHRA and the project – with construction activities in full swing and spending plans, albeit revised from initial objectives, being achieved with further funding offered and used as hoped – the coming 12 months held much promise.

June 2021

After months of negotiations, the CHSRA says it has secured the return of funding taken from it by President Trump’s administration a few years earlier.


Newsom said: “Restoring nearly $929m in grant funding back to the California High-Speed Rail project will continue to spur job creation, advance the project and move the state one step closer to getting trains running in California as soon as possible.”


Throughout the remainder of the year, the project continues to advance. Further work begins or is completed, political figures throw their weight behind the project and it wins several architecture and sustainability awards.

Construction of the 3,700-foot Cedar Viaduct in Fresno. Credit: California High-Speed Rail Authority

Project construction today continues and the initiative is supported by further federal monies – with grant applications still being made. 


However, criticism from some quarters continues to be levelled, with ongoing concerns about delays, overspending, and environmental impacts. To be fair, the economic climate hasn’t helped, with inflation not seen for generations adding to the problems. 

 

In October of last year, speaking of its track and systems procurement strategy, the CHSRA said it hoped to be able to restart the process in 2023, citing inflationary pressures and supply chain issues for its decision to review in light of “unstable and volatile supply and pricing in the current market”.


What happens next really is anyone’s guess. The project has been fraught with difficulty – some out of managers’ hands, others firmly their responsibility according to the most vocal of critics. What’s for sure is that this story will continue to move forward. 

Editors Note: The California High-Speed Rail Project has a long story and this is by no means an exhaustive list of the events to date, rather a collection of our noteworthy moments. Add to conversation @FutureRail_Mag